PlannerCorePATHWhat is driving your milestone?
1.0 beta
Driving path analysis for Primavera P6

What is really driving your milestone?

Open a P6 export and choose any milestone. PATH follows the logic back from it, measures every link on the programme's own working calendars, and shows the chain that holds the date, with the float every other activity has before it starts to matter.

Nothing is uploaded. The file is read on this computer and is gone when you close the tab.

Drop your XER here

or choose a file from your computer

Primavera P6 .xer exports, up to 80 MB
01

The chain, not the float column

Total float answers to the end of the project. PATH answers to the milestone you choose, so an interim handover gets its own driving chain and its own float.

02

Measured in working time

Every link is tested on the successor's calendar, with lag counted on the calendar your schedule options name. Weekends, shutdowns and 24 hour lags are handled, not guessed.

03

Evidence you can hand over

Each link carries its dates, its float and a plain reason. Download the review pack as a formatted Excel workbook for the meeting.

Take it to the meeting

Download the review pack

A formatted Excel workbook for this milestone: summary, the driving chain in order, every upstream activity with its float to the milestone, the evidence behind each link, review notes and the method.